Contract Agreement Amount

Rs. 33,20,24,320

Physical Progress

99.00%

Financial Progress

102.27%

Remaining Payment

Rs. -2

Dhading Gorkha Road Project Package 2

Office: आयोजना निर्देशनालय, ए.डि.वि., विशालनगर, काठमाण्डौ (77)

Fiscal Year: 073-74

99.00%

Contract Date: 28-Dec-16

Start Date: 12-Jan-17

Completion Date: 30-Sep-2019 (EOT Done)

Project Description

No description available.