Contract Agreement Amount
Rs. 23,49,60,269
Physical Progress
100.00%
Financial Progress
102.16%
Remaining Payment
Rs. -2
Construction of Black top road and structure works.
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 071-72
Contract Date: 17-Mar-15
Start Date: 17-Mar-15
Completion Date: 13-Apr-2023 (EOT Done)