Contract Agreement Amount
Rs. 8,86,32,143
Physical Progress
100.00%
Financial Progress
101.93%
Remaining Payment
Rs. -1
Construction of Pre-Stressed RCC Bridge over Lakhandehi Bridge along Belhi-Sundarpur Road, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 073-74
Contract Date: 17-Mar-17
Start Date: 17-Mar-17
Completion Date: 11-Oct-2022 (EOT Done)
Project Description
No description available.