Contract Agreement Amount

Rs. 1,89,43,232

Physical Progress

100.00%

Financial Progress

101.55%

Remaining Payment

Rs. -1

Road Upgrading Works on Koshi Highway(Hile to Basantpur Section)

Office: योजना तथा अनुगमन महाशाखा (HMIS तथा ICT शाखा) (6)

Fiscal Year: 079-80

100.00%

Contract Date: 6-Dec-22

Start Date: 6-Dec-22

Completion Date: 13-Jun-2023 (EOT Not Done)

Project Description