Contract Agreement Amount
Rs. 1,89,43,232
Physical Progress
100.00%
Financial Progress
101.55%
Remaining Payment
Rs. -1
Road Upgrading Works on Koshi Highway(Hile to Basantpur Section)
Office: योजना तथा अनुगमन महाशाखा (HMIS तथा ICT शाखा) (6)
Fiscal Year: 079-80
Contract Date: 6-Dec-22
Start Date: 6-Dec-22
Completion Date: 13-Jun-2023 (EOT Not Done)
Project Description
No description available.