Contract Agreement Amount
Rs. 5,26,34,566
Physical Progress
100.00%
Financial Progress
101.42%
Remaining Payment
Rs. -1
Upgrading widening of Belhiya-Butwal Road (Ch.26+940~27+250)
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 078-79
Contract Date: 3-May-22
Start Date: 3-May-22
Completion Date: 03-Nov-2023 (EOT Not Done)
Project Description
No description available.