Contract Agreement Amount
Rs. 80,21,590
Physical Progress
36.31%
Financial Progress
101.11%
Remaining Payment
Rs. -1
Upgrading and Rehabiliation of Road in Khodpe-Bitthad Section of Khodpe Chainpur Highway Ch: 0+000 to 33+000 (NH-64)
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 078-79
Contract Date: 14-Feb-22
Start Date: 14-Feb-22
Completion Date: 13-Jun-2022 (EOT Not Done)
Project Description
No description available.