Contract Agreement Amount
Rs. 25,78,987
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Rigid Pavement and Side Drain Works at BA Cement Quarry Site Access Road, Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 3-Feb-20
Start Date: 18-Feb-20
Completion Date: 14-Jun-2020 (EOT Not Done)
Project Description
No description available.