Contract Agreement Amount
Rs. 41,03,117
Physical Progress
35.00%
Financial Progress
100.64%
Remaining Payment
Rs. 0
Road widening & upgrading works atJagadamba Tower Purano Bato Nikosera
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 25-Apr-21
Start Date: 25-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.