Contract Agreement Amount
Rs. 3,22,02,147
Physical Progress
100.00%
Financial Progress
100.53%
Remaining Payment
Rs. 0
Construction of 2-Webbed RC Cast In Situ Bridge (1x20) Over Manglohiya (Jalad) Khola along Janakpur Sub-Metropolitan City - 25 Lohana Tole to Dhanauji Road, Dhanusha
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 077-78
Contract Date: 14-Mar-21
Start Date: 15-Mar-21
Completion Date: 15-Mar-2023 (EOT Not Done)
Project Description
No description available.