Contract Agreement Amount

Rs. 1,08,72,080

Physical Progress

100.00%

Financial Progress

100.51%

Remaining Payment

Rs. 0

Construction of RCC Box Culvert over Dipini Khola and Harchana Khola, Jhapa.

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 074-75

100.00%

Contract Date: 11-Dec-17

Start Date: 11-Dec-17

Completion Date: 15-Jul-2018 (EOT Not Done)

Project Description

No description available.