Contract Agreement Amount

Rs. 2,31,99,989

Physical Progress

100.00%

Financial Progress

100.40%

Remaining Payment

Rs. 0

Construction of Road Structure,Road way Excavation,Grade/Bend Improvement along Jhyalbas to pokhari section of Dhauwadi Falam khanisthal to MRM Road,Nawalpur

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

100.00%

Contract Date: 1-Dec-19

Start Date: 4-Dec-19

Completion Date: 02-Jul-2020 (EOT Not Done)

Project Description

No description available.