Contract Agreement Amount
Rs. 8,78,98,580
Physical Progress
100.40%
Financial Progress
100.38%
Remaining Payment
Rs. 0
शंकरमाली/अकेला जे.भि.
Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)
Fiscal Year: 072-73
Contract Date: 6-Jul-16
Start Date: 7-Jul-16
Completion Date: 17-Oct-2019 (EOT Done)
Project Description
No description available.