Contract Agreement Amount
Rs. 1,15,35,840
Physical Progress
0.00%
Financial Progress
100.38%
Remaining Payment
Rs. 0
Road Saftey works along SRN/SURNs, Lalitpur
Office: हेभिईक्युपमेन्ट डिभिजन, सुनसरी (37)
Fiscal Year: 079-80
Contract Date: 10-May-23
Start Date: 10-May-23
Completion Date: 12-Aug-2023 (EOT Not Done)
Project Description
No description available.