Contract Agreement Amount
Rs. 4,80,58,849
Physical Progress
27.84%
Financial Progress
100.36%
Remaining Payment
Rs. 0
Road Protection work along Karnali HIghway Ch 133+100, 133+300, 140+450, 140+600,141+100,143+400,144+000,144+350,155+900,156+200,158,300,159+200,160+900,161+100 kalikot
Office: सडक डिभिजन, कपिलवस्तु (29)
Fiscal Year: 079-80
Contract Date: 2-May-23
Start Date: 2-May-23
Completion Date: 01-May-2024 (EOT Not Done)
Project Description
No description available.