Contract Agreement Amount

Rs. 1,62,39,420

Physical Progress

0.00%

Financial Progress

100.30%

Remaining Payment

Rs. 0

Construction of Side drain works in Banepa- Panauti Road

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 074-75

0.00%

Contract Date: 2-Apr-18

Start Date: 2-Apr-18

Completion Date: 11-Jan-2019 (EOT Done)

Project Description