Contract Agreement Amount
Rs. 56,90,240
Physical Progress
100.00%
Financial Progress
100.15%
Remaining Payment
Rs. 0
Road Construction Woks along Birgunj 31 ko yashlampur dekhi Janata sadak sama ko sadak , Parsa
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 079-80
Contract Date: 4-Dec-22
Start Date: 4-Dec-22
Completion Date: 13-Jun-2023 (EOT Not Done)
Project Description
No description available.