Contract Agreement Amount
Rs. 5,62,25,950
Physical Progress
0.00%
Financial Progress
100.13%
Remaining Payment
Rs. 0
Periodic Maintenance works on Hetauda Lothar Road
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 075-76
Contract Date: 18-Mar-19
Start Date: 18-Mar-19
Completion Date: 26-Jun-2019 (EOT Not Done)