Contract Agreement Amount
Rs. 2,42,83,144
Physical Progress
99.91%
Financial Progress
100.11%
Remaining Payment
Rs. 0
Construction of Pavement & Structural Works, Kailali (Ch.45+850 to 47+300)
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 080-81
Contract Date: 3-Jan-24
Start Date: 3-Jan-24
Completion Date: 04-Jul-2024 (EOT Not Done)
Project Description
No description available.