Contract Agreement Amount

Rs. 2,92,36,595

Physical Progress

101.00%

Financial Progress

100.08%

Remaining Payment

Rs. 0

Construction of RCC CIS bridge over Gharelukhola.

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 075-76

101.00%

Contract Date: 14-Jul-19

Start Date: 21-Jul-19

Completion Date: 18-Oct-2020 (EOT Not Done)

Project Description

No description available.