Contract Agreement Amount

Rs. 46,79,254

Physical Progress

95.00%

Financial Progress

100.07%

Remaining Payment

Rs. 0

eactive Maintenance works along Sanagaun - Thaiba Road &Gwarko-Krishna mandir-ImadolPawanprakriti school

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 076-77

95.00%

Contract Date: 24-Feb-20

Start Date: 24-Feb-20

Completion Date: 16-Dec-2020 (EOT Done)

Project Description

No description available.