Contract Agreement Amount
Rs. 67,72,697
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Retaining and Drainage Structures work along Duhabi-Inaruwa sadak, Sunsari
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 079-80
Contract Date: 4-Dec-22
Start Date: 5-Dec-22
Completion Date: 30-Jun-2023 (EOT Not Done)
Project Description
No description available.