Contract Agreement Amount
Rs. 1,23,08,767
Physical Progress
99.90%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Repairs and Maintenance work of Budhi Khola Bridge and Gachiya Khola Bridge along Mahendra Rajmarga
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 077-78
Contract Date: 22-Feb-21
Start Date: 22-Feb-21
Completion Date: 14-Jul-2021 (EOT Done)
Project Description
No description available.