Contract Agreement Amount
Rs. 1,16,52,128
Physical Progress
99.74%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Maintenance works ( side drain, gabion and masonary works) in Kanti Rajmarga
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 078-79
Contract Date: 7-Apr-22
Start Date: 7-Apr-22
Completion Date: 15-Dec-2022 (EOT Done)
Project Description
No description available.