Contract Agreement Amount
Rs. 7,29,73,564
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Asphalt concrete overlay and extension of existing road at Ch.1+208(Eye Hospital) to 4+474(Baruwa Bridge)
Office: Unknown (1)
Fiscal Year: 079-80
Contract Date: 28-Nov-22
Start Date: 28-Nov-22
Completion Date: 05-Jul-2023 (EOT Done)