Contract Agreement Amount

Rs. 22,75,367

Physical Progress

0.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

दाङ सिमेन्ट फैक्ट्री क्वारी साइट सडक दाङ

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 076-77

0.00%

Contract Date: 17-Mar-20

Start Date: 18-Mar-20

Completion Date: 04-Jul-2020 (EOT Not Done)

Project Description

No description available.