Contract Agreement Amount
Rs. 1,27,46,661
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
construction of roadway structural and blacktop works in manthali natila fulasi doramba tokarpur road (ch.4+910- 5+805)
Office: डिभिजन सडक कार्यालय, खुर्कोट (185)
Fiscal Year: 076-77
Contract Date: 2-Jun-20
Start Date: 3-Jun-20
Completion Date: 13-Jan-2021 (EOT Not Done)
Project Description
No description available.