Contract Agreement Amount
Rs. 40,51,795
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Upgrading works of 21 kilo lisankhu wafal sukute road
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 076-77
Contract Date: 19-Dec-19
Start Date: 19-Dec-19
Completion Date: 12-Apr-2020 (EOT Not Done)
Project Description
No description available.