Contract Agreement Amount
Rs. 41,03,197
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Road widening&upgrading works at Araniko Rajmarga Nalinchowk khadka gaun paakha gaun mahat gaun kakrabari sadak
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 10-May-21
Start Date: 10-May-21
Completion Date: 06-Oct-2021 (EOT Not Done)
Project Description
No description available.