Contract Agreement Amount
Rs. 35,70,789
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Road Safety Works along Birgunj Bypass Road, Parsa
Office: यान्त्रिक कार्यालय, झापा (43)
Fiscal Year: 079-80
Contract Date: 4-Apr-23
Start Date: 4-Apr-23
Completion Date: 05-Jul-2023 (EOT Not Done)
Project Description
No description available.