Contract Agreement Amount

Rs. 52,97,049

Physical Progress

0.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Road Construction Works on Basatpur Katahariya Kabaibot Pipdari Patrahati Padam Road Bara

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 076-77

0.00%

Contract Date: 18-Nov-19

Start Date: 18-Nov-19

Completion Date: 04-Jul-2020 (EOT Not Done)

Project Description

No description available.