Contract Agreement Amount

Rs. 3,13,52,135

Physical Progress

100.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Rapti Highway Shitalpati-Khaula Section (Ch 106+000 to 114+000) in Salyan District.

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 078-79

100.00%

Contract Date: 28-Feb-22

Start Date: 28-Feb-22

Completion Date: 03-Jul-2023 (EOT Done)

Project Description

No description available.