Contract Agreement Amount
Rs. 1,91,09,494
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Periodic Maintenance of East West Highway, Ch 1018+410 to 1027+670, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 29-Dec-19
Start Date: 13-Jan-20
Completion Date: 11-Oct-2020 (EOT Done)
Project Description
No description available.