Contract Agreement Amount
Rs. 6,31,47,391
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Lohandra Khola Bridge Construction work Katari 5 Siswani 7, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 074-75
Contract Date: 26-Mar-18
Start Date: 26-Mar-18
Completion Date: 05-Feb-2018 (EOT Not Done)
Project Description
No description available.