Contract Agreement Amount
Rs. 9,60,000
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Detailed engineering survey, soil investigation, detailed design of Khanche Bhachok river bridge including approach roads, river-training and bridge protection works, and preparation of working drawings and other necessary documents.
Office: डुम्रे बेसीशहर चामे सडक योजना, बेसीशहर लमजुङ (299)
Fiscal Year: 076-77
Contract Date: 1-Apr-20
Start Date: 1-Apr-20
Completion Date: 18-Oct-2020 (EOT Not Done)