Contract Agreement Amount
Rs. 46,93,189
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Construction of Masonry Structure, Gabion Works & Pipe Culverts upto Gravel Standards along Marin 5 Badiman Pramanipur Section, Sindhuli
Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)
Fiscal Year: 080-81
Contract Date: 18-Oct-23
Start Date: 18-Oct-23
Completion Date: 14-Jun-2024 (EOT Not Done)