Contract Agreement Amount
Rs. 2,99,468
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Construction of Gabion works in Umathirtha Kashitar Lahacheur Kau Bauddhagumba Road
Office: डिभिजन सडक कार्यालय, खुर्कोट (185)
Fiscal Year: 077-78
Contract Date: 9-Mar-21
Start Date: 16-Mar-21
Completion Date: 14-Jun-2021 (EOT Not Done)
Project Description
No description available.