Contract Agreement Amount
Rs. 35,82,443
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Blacktopped Road Construction Works on Sanischare bajar Singari Mahadeva sadak,Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 076-77
Contract Date: 11-Dec-19
Start Date: 11-Dec-19
Completion Date: 12-May-2020 (EOT Done)
Project Description
No description available.