Contract Agreement Amount

Rs. 3,68,47,585

Physical Progress

82.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Construction of RCC Bridge over Betaha Khola (1 No.*15 m Span, Total Length 16.20 m) along Rajbiraj Balan Road, Saptari

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)

Fiscal Year: 074-75

82.00%

Contract Date: 13-Jul-18

Start Date: 28-Jul-18

Completion Date: 10-Sep-2024 (EOT Done)

Project Description

No description available.