Contract Agreement Amount

Rs. 9,73,193

Physical Progress

96.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Struuctural works on Bannigadhi Ga. Pa. 2-4 Achham, Janalakot-Timilsen Ring Road

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 079-80

96.00%

Contract Date: 9-Apr-23

Start Date: 9-Apr-23

Completion Date: 08-Jun-2023 (EOT Not Done)

Project Description

No description available.