Contract Agreement Amount

Rs. 34,18,547

Physical Progress

100.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Arunkhola Tamaspur Baguwan Dumkibas Sadak, Nawalpur

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

100.00%

Contract Date: 11-Nov-19

Start Date: 11-Nov-19

Completion Date: 17-May-2020 (EOT Not Done)

Project Description

No description available.