Contract Agreement Amount

Rs. 87,38,679

Physical Progress

0.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Road Protection Works in Suryabinayak Dhulikhel, Dhulikhel-Sindhuli-Bardibas Road Project at different chainage of section- I (0+000~37+000)

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 078-79

0.00%

Contract Date: 21-Feb-22

Start Date: 21-Feb-22

Completion Date: 04-Aug-2022 (EOT Not Done)

Project Description

No description available.