Contract Agreement Amount

Rs. 33,88,505

Physical Progress

99.78%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Construction of Black Topped Road along Kisanchowak-Tandi-Ramite Sadak Morang.

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 076-77

99.78%

Contract Date: 28-Nov-19

Start Date: 28-Nov-19

Completion Date: 12-May-2020 (EOT Done)

Project Description

No description available.