Contract Agreement Amount
Rs. 54,11,538
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Construction of footpath, drain asphalt overlay, black top works on Pepsicola sallaghari, bhaktapur nagarkot road and sallaghari durbar square road.
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 068-69
Contract Date: 29-Nov-11
Start Date: 29-Nov-11
Completion Date: 12-Jun-2012 (EOT Not Done)