Contract Agreement Amount
Rs. 26,36,289
Physical Progress
100.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Road protection and slab culvert works on Bidur Na.Pa. Dandagaun Dadare khola, Nuwakot
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 079-80
Contract Date: 31-Jan-23
Start Date: 31-Jan-23
Completion Date: 30-Jun-2023 (EOT Not Done)