Contract Agreement Amount
Rs. 57,73,936
Physical Progress
0.00%
Financial Progress
100.00%
Remaining Payment
Rs. 0
Blacktop Works along BalmikiChakrapath, Nawalpur
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 9-Jan-20
Start Date: 9-Jan-20
Completion Date: 07-Jul-2020 (EOT Not Done)
Project Description
No description available.