Contract Agreement Amount

Rs. 1,11,46,650

Physical Progress

100.00%

Financial Progress

100.00%

Remaining Payment

Rs. 0

Road upgrading and maintenance works at Thimi Bode.

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 078-79

100.00%

Contract Date: 19-May-22

Start Date: 19-May-22

Completion Date: 18-Oct-2022 (EOT Not Done)

Project Description

No description available.