Contract Agreement Amount

Rs. 1,64,42,105

Physical Progress

100.00%

Financial Progress

99.99%

Remaining Payment

Rs. 0

Road upgrading works at Hanumante khola ko nayapulbata chakophanthudai katunje jane sadak su.na pa 4

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 078-79

100.00%

Contract Date: 11-Mar-22

Start Date: 11-Mar-22

Completion Date: 14-Jul-2022 (EOT Not Done)

Project Description

No description available.