Contract Agreement Amount
Rs. 30,69,075
Physical Progress
100.00%
Financial Progress
99.99%
Remaining Payment
Rs. 0
Road Improvement Works (Pavement & drain works) along East-West Highway Sarawal-1 Basabasahi to Sunawal-11 MishrauliPuranoBato-Baluwa-Kerwani-Kanchitol-Baba Bardagoriya- Hira Gunj to Sunawal-13 BaderaChowk Road
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 079-80
Contract Date: 19-Dec-22
Start Date: 19-Dec-22
Completion Date: 19-Jun-2023 (EOT Not Done)
Project Description
No description available.