Contract Agreement Amount

Rs. 30,69,075

Physical Progress

100.00%

Financial Progress

99.99%

Remaining Payment

Rs. 0

Road Improvement Works (Pavement & drain works) along East-West Highway Sarawal-1 Basabasahi to Sunawal-11 MishrauliPuranoBato-Baluwa-Kerwani-Kanchitol-Baba Bardagoriya- Hira Gunj to Sunawal-13 BaderaChowk Road

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 079-80

100.00%

Contract Date: 19-Dec-22

Start Date: 19-Dec-22

Completion Date: 19-Jun-2023 (EOT Not Done)