Contract Agreement Amount
Rs. 40,65,526
Physical Progress
100.00%
Financial Progress
99.99%
Remaining Payment
Rs. 0
Jhim Nadi Bridge Gair, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 16-Apr-20
Start Date: 16-Apr-20
Completion Date: 09-Jul-2020 (EOT Not Done)
Project Description
No description available.