Contract Agreement Amount
Rs. 66,64,843
Physical Progress
100.00%
Financial Progress
99.99%
Remaining Payment
Rs. 0
Road Improvement Works along Harkapur-14 Kilo Ratanpur Road, Nawalpur
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 10-Jun-20
Start Date: 10-Jun-20
Completion Date: 12-Feb-2021 (EOT Not Done)
Project Description
No description available.